Construction diary.

Project progress and the latest news — open and unfiltered.

Location

The hangar at Punane 18.

Where the arena rises. A former industrial hangar — the bones that become the pitch.

Hangar interior with overhead crane01 / 05
Hangar empty floor, wide view02 / 05
Hangar wide interior03 / 05
Hangar door and rails04 / 05
Hangar side, overhead crane closeup05 / 05

Photographed May 2026. The space before works begin.

Project progress

What's done and what's next.

An open chronicle of the build. Updated as we go.

  1. March — April 2026

    Design and documentation

    Architecture, permits and technical documentation. Contractor and equipment selection.

  2. May 2026

    Contracts signed

    Long-term lease signed. Construction contracts in place. The project is officially underway.

  3. June 1, 2026

    Support campaign launched

    Fundraising is open at togethertogoals.com. 1,440 pitch squares available for named support — from €10.

    Open the campaign
  4. June — August 2026

    Construction and installation

    Artificial turf laid, LED 500 lux lighting installed, goals and stands set up. In parallel — finishing the changing rooms and fitness facility.

  5. October 2026

    Grand opening

    Both pitches open. First trainings and tournaments. Names and logos of every supporter placed in the arena.